Nissan Assembly Plant

Nissan Assembly Plant

Yates Construction and our joint venture partner provided construction services for Mississippi’s first automotive manufacturing facility. This two-phase project totaling 3.3 million SF consists of three buildings that perform metal parts stamping, robotic welding of the entire sheet metal body, and final vehicle assembly. In total, 18,000 tons of structural steel, 90,000 cubic yards of reinforced concrete, 18,000 tons of air conditioning, and two million linear feet of electrical conductor were installed. The project’s scope also included equipment pits, a primary switch gear, a water tank, utility trestles, a process tank farm, and caisson foundations for all presses and production conveyors.

  • Owner

    Nissan North America

  • Size

    3.3 Million SF

  • Markets

    Automotive,

Owner

Nissan North America

Size

3.3 Million SF

Role

General Construction

Markets

Automotive,